The word's longest railway tunnel is being constructed here.

We are building the future.

Status of Work on the Gotthard and Ceneri

03.07.2010

Vezia

Vezia

As of July 1, 2010, of the total of 151.84 km of tunnels, galleries and passages of the Gotthard Base Tunnel, 146.6 km, or 96.6 %, had been excavated. The total amount driven in June 2010 was 531 m.

Of the total of 39.78 km of the Ceneri Base Tunnel, at the end of June 2010, 8,344m, or 21%, had been excavated.

Ceneri - State of excavation

Watch the tunnellers at work - the new documentary film "AlpTransit Gotthard 2009" makes it possible. The milestones and progress achieved in 2009 on the construction sites of the Gotthard and Ceneri tunnels are available on DVD.